Why do automation projects fail? 5 avoidable mistakes in the engineering phase

When an automation project runs late or over budget, the chosen PLC is almost never to blame. The problems usually start months earlier, in engineering and management decisions that can be avoided. These are the five mistakes we see most often and how management can prevent them.

Back to Blog

What it means for a project to "fail"

Few automation projects fail outright: in the end the machine starts and the line produces. Failure is usually quieter and more expensive. Commissioning drags on for weeks, extras appear that nobody had budgeted for, the line takes months to reach its target output, or the system is so poorly documented that every breakdown depends on one person.

After many projects, both our own and ones inherited from other integrators, we have reached one conclusion: technology is rarely the problem. Siemens, Beckhoff, Wago and CODESYS all work. What fails is how the work is defined, managed and handed over. And that is decided in the engineering phase, long before anyone connects a wire.

Mistake 1: programming without a functional specification

This is the most common mistake and the most expensive one. A quote is approved on the basis of a general description ("automate the packing line") and the integrator starts programming based on what they understand. The important questions, such as what happens if a sensor fails, how an interrupted cycle is recovered or which recipes are needed, get answered on site, during commissioning, with production waiting.

The tool that prevents this is the functional specification: a document that describes, in language production and maintenance staff understand, how the installation must behave in each operating mode. It does not need to be long, but it must cover:

  • Operating modes. Automatic, manual, maintenance, controlled start-up and shutdown, and how to move between them.
  • Sequences and interlocks. Which conditions must be met for each movement and what happens if they stop being met.
  • Alarms and recovery. Which faults are detected, how they are signalled and how production resumes.
  • Interfaces. Which data is exchanged with other machines, the SCADA and the ERP.
  • Acceptance criteria. How compliance will be verified: throughput, availability, specific tests.

Writing it takes days. Skipping it usually costs weeks. It also makes quotes comparable: if three integrators quote against the same specification, you compare prices; if they quote against an idea, you compare interpretations. We cover this further in our industrial automation cost guide.

Mistake 2: accepting changes without managing them

Changes are inevitable and not a problem in themselves. The problem is how they are made. A production manager asks on the shop floor for "the conveyor to wait two more seconds", the programmer changes it on the spot, and nobody records it. Multiply that by fifty and the result is a program that no longer matches the specification, out-of-date documentation and an argument at the end of the project about what was and was not included.

The fix is not bureaucracy, just minimal discipline:

  1. Every change is requested in writing, even if only by email or a line in a shared log.
  2. It is assessed in hours, materials and schedule impact before it is made.
  3. It is approved by whoever has the authority to do so, not by whoever happens to be standing at the machine.
  4. It is reflected in the specification and the final documentation.

Small changes can be grouped and approved together, but none should exist only in the memory of the person who made it.

Mistake 3: interfaces nobody owns

A modern line rarely has a single supplier. There is a filler manufacturer, another for the palletiser, an integrator for the conveyors, an IT company for the network and the ERP. Each one delivers their machine. And the boundaries between them, such as handshake signals, protocols and the plant network, sit in no man's land until something does not work.

Those boundaries are where most commissioning days are lost. To avoid it:

  • Appoint an integration lead, in-house or external, with authority over all suppliers.
  • Define an interface document listing every signal, its meaning, direction and protocol, before anyone programs.
  • Fix the network architecture from the start: addressing, segmentation and remote access, as explained in industrial OT/IT cybersecurity.
  • Choose open protocols when several brands are involved; our OPC UA guide explains why it simplifies integration.

The same applies to business systems: if the goal is to bring production data into the ERP, define it during engineering rather than as a later add-on. We cover this in integrating ERP with plant data.

Mistake 4: testing on site for the first time

When the first time the program runs with real signals is during commissioning, every error shows up at once, with production stopped. It is the most expensive, highest-pressure moment to fix anything.

Testing beforehand completely changes the risk profile:

  • Simulation. With tools such as PLCSIM or a simple process model, sequences, alarms and modes are tested before hardware exists.
  • FAT (factory acceptance test). The cabinet and program are tested in the workshop, signal by signal, with the customer present and a signed protocol.
  • SAT (site acceptance test). The essentials are repeated at the real site, already confident that the foundation works.

When migrating existing systems, it also pays to run in parallel with the old system and always have a rollback plan. That is how we work when migrating a legacy SCADA or moving from S7-300 to S7-1500. And when functional safety is involved, validating the safety functions cannot be improvised, as detailed in our S7-1500 Safety guide.

Mistake 5: a handover that leaves the customer dependent

The project ends, the integrator leaves and, six months later, nobody on site knows how to change a recipe or interpret an alarm. The program has no comments, the schematics do not reflect what is installed and the licences are in someone else's name. Technically the project was delivered; in practice, the plant is now tied to one supplier.

A good project close-out includes, at a minimum:

  • Final programs for PLC, HMI and SCADA, commented and matching the installed version.
  • As-built electrical schematics that match the real cabinet.
  • A list of critical spare parts, because documentation is of little use without a replacement on the shelf. We explain why in the importance of spare parts.
  • Training for operators and maintenance, tailored to each profile.
  • Licences and access in the customer's name.
  • A support plan for the first weeks, ideally with remote support.

And if the plant has many machines from different suppliers, the best long-term protection is an in-house programming standard. We explain it in detail in how to standardise PLC programming in your plant.

Warning signs before you sign

Many of these mistakes can be spotted at the quotation stage. Be wary when:

  • The quote does not mention a functional specification, FAT or final documentation.
  • The commissioning schedule looks too optimistic for the scope.
  • Nobody asks about interfaces with other machines or systems.
  • It is unclear who your technical contact will be for the whole project.
  • The supplier cannot show you documentation from previous projects.

If you are comparing suppliers, our guide on how to choose an industrial automation company lists the questions worth asking.

Frequently asked questions

What is the most common cause of delay in an automation project?

An incomplete functional specification. When the behaviour of the installation is not defined in writing before programming starts, decisions get made during commissioning, which is the most expensive and highest-pressure moment to make them.

How should changes be controlled in an automation project?

With a simple procedure: every change is recorded in writing, assessed for cost and schedule impact, and approved before it is carried out. Small changes can be grouped together, but none should be made on the strength of a conversation on the shop floor alone.

Is it worth paying for a FAT before commissioning?

Almost always. Testing the program and the cabinet in the workshop, with simulation or real hardware, catches errors when fixing them costs office hours rather than days of plant downtime.

What should the customer receive when an automation project closes?

At a minimum: final PLC and HMI programs, as-built electrical schematics, bills of materials and spare parts lists, an operating manual, staff training and licences in the customer's name. It is worth writing this into the contract.

Conclusion

Successful automation projects are not the ones with the most advanced technology, but the ones that are clearly defined, manage change, have someone who owns the interfaces, are tested before reaching the plant and are handed over so the customer can maintain them. None of those five things is technically difficult. All of them depend on decisions made at the start.

At Bluemation we support projects from specification to commissioning, through our consulting and PLC programming services. If you are preparing a project, or have one that is not progressing as expected, tell us where it stands and we will help you get it back on track.